Answer:Consider two processes P, and P2 where pi=50,lh=25and p2=75,f2=30.If I were assigned a higher priority than Pi,then the
following scheduling events happen under rate monotonic scheduling.P1 is scheduled att=0,P2is scheduled att=25,Ph is scheduled at
t=50,and P2 is scheduled att=75.P2 is not scheduled early enoughto meet its deadline.The earliest deadline schedule performs the fol-
lowing scheduling events:Pi is scheduled att=0,a is scheduled atf=25,P,is scheduled att=55,and so on.This schedule actually meets the deadlines and therefore earliest deadline first scheduling is more effective than the rate monotonic scheduler.
Answer:Consider two processes P, and P2 where pi=50,lh=25and p2=75,f2=30.If I were assigned a higher priority than Pi,then the
following scheduling events happen under rate monotonic scheduling.P1 is scheduled att=0,P2is scheduled att=25,Ph is scheduled at
t=50,and P2 is scheduled att=75.P2 is not scheduled early enoughto meet its deadline.The earliest deadline schedule performs the fol-
lowing scheduling events:Pi is scheduled att=0,a is scheduled atf=25,P,is scheduled att=55,and so on.This schedule actually meets the deadlines and therefore earliest deadline first scheduling is more effective than the rate monotonic scheduler.