Identify the following environments as either hard or soft real-time.

a.Thermostat in a household.

b.Control system for a nuclear power plant.

c.Fuel economy system in an automobile.

d.Landing system in a jet airliner.

推荐

Answer:Hard real-time scheduling constraints are required for the nuclear power plant and for the jet airliner.In both settings,a delayed

reaction could have disastrous consequences and therefore the sched-uler would need to satisfy real-time scheduling requirements.On the

other hand,the thermostat and the fuel economy system can be oper-ated within the context of a scheduler that provides only soft real-time

constraints.Delayed triggering of these devices would only result in suboptimal use of resources or a slight increase in discomfort.